A Liebherr MK 88-4.1 mobile construction crane, deployed by the Ponticelli group of companies, carried out repairs on a historic bridge in Paris and reinstalled a damaged piece of artwork. The work took place on the Pont-Neuf, where the crane helped repair the installation 'La Caverne du Pont-Neuf' by French artist JR.
The temporary inflatable artwork, roughly 120 metres long, was created as a tribute to the wrapping of the Pont-Neuf by artists Christo and Jeanne-Claude, first installed in 1985. In early June, violent gusts of wind and hail damaged parts of its outer shell. According to Ponticelli, the company was on site within hours of the damage to work out the best technical solution together with the client.
"As well as repairing the tarpaulin, we had to carry out a lifting operation safely in almost constant wind and under considerable time pressure," said Louis-Arthur de Quatrebarbes, head of the handling and lifting agency at Ponticelli.
The Pont-Neuf is the oldest bridge in Paris, offering limited working space and welcoming large numbers of daily visitors. Load-distribution plates were used to reduce ground pressure, while safety and traffic management measures supported the operation.
The team initially planned to use a larger Liebherr mobile crane, but the tight conditions led it to bring in the MK 88-4.1 instead. Its 45-metre trolley jib reached all the damaged areas of the structure, and the four-axle design allowed it to be relocated easily from one side of the bridge to the other, where storm damage had also occurred. The crane's short set-up time and compact outrigger system further helped the work.
The crane cab could move at working height, giving the operator a clear view of the approximately 18-metre-high structure and the rope access technicians. Boom-mounted spotlights provided illumination during night-time operations.
Repair work was carried out over four night shifts. Damaged fabric sections weighing between 200 and 400 kilograms were lifted and reattached in collaboration with rope access technicians. Because the site sat in a wind corridor along the River Seine, weather conditions were monitored continuously, and the crane operator and technicians stayed in radio contact throughout.
Before work began, the team carried out site inspections, load calculations and collision analyses of surrounding buildings. A 360-degree test confirmed the planned crane positioning.
For Ponticelli, the project went beyond a conventional lifting job. "We are proud to have been part of this work of art. To quote JR: 'The installation of the artwork is part of the artwork' — and so is the crane," de Quatrebarbes said, adding that the visually striking deployment of the MK crane created a magical moment.
Liebherr said the project demonstrated the MK 88-4.1's strengths in demanding inner-city work, where heritage conservation, confined spaces and a high level of precision combine to call for a mix of reach, compactness and flexibility.